Do these include the crane?
No. These are crew hours to set the piece. Crane, lift equipment, rigging and operator are separate.
Construction estimating tool
Field erection hours per piece by scope — beams, columns, stairs, guardrail, fence, canopy and misc metals — with the observed spread on every rate. No account required.
430 priced estimates across 119 jobs
Estimated hours
800
Range 400 to 1,200 hours (p10–p90). Price the range, not the midpoint, on anything you have not built before.
| Scope | p10 | Median | p90 | Obs. |
|---|---|---|---|---|
| hr / pc | 4 | 8 | 12 | 6,008 |
| hr / pc | 0.975 | 8 | 8.4 | 1,354 |
| hr / pc | 4 | 5 | 8.248 | 2,669 |
| hr / pc | 0.5 | 1 | 1 | 43 |
| hr / pc | 3 | 6 | 6 | 2,123 |
| hr / pc | 3.4 | 6 | 6.89 | 10,039 |
| hr / pc | 4 | 4 | 6 | 312 |
| hr / pc | 1.9 | 3 | 8 | 4,907 |
| hr / pc | 2.526 | 8 | 12 | 15,538 |
Computed over 43,060 observed records across 430 priced estimates across 119 jobs. These are observed rates from real priced estimates — not an industry average and not a benchmark. They are a starting point for your own estimate, never a substitute for one, and they carry no money: labour rates, markup and margin are yours.
A stair assembly and a beam of the same weight are different install problems. Scope beats tonnage every time in the field.
Field hours track crane picks and connections, so the unit is pieces, not pounds.
Access, height, occupied buildings, phasing and out-of-sequence work are not in these numbers and routinely dominate them.
No. These are crew hours to set the piece. Crane, lift equipment, rigging and operator are separate.
Because the work genuinely varies. Canopy install runs from under an hour to over eight per piece depending on access and height. Where the spread is wide the confidence is marked low, and you should price your own conditions.
Hours are hours. Wage rates are separate and are yours — this tool carries no money at all.
Anvil connects your rates, your shop history and your estimates.