Construction estimating tool

Fabrication operation rates

Hours per unit for the discrete operations that build up a fabrication estimate — drilling, stud welding, bolt-up and fasteners. Price connection work by count instead of guessing a percentage.

1,617 observed lines · 429 priced estimates

Estimated hours

0

Range to 0 hours (p10–p90). Price the range, not the midpoint, on anything you have not built before.

Every published rate

Scopep10Medianp90
hr / piece00
hr / each0.16670
hr / each0.08330
hr / each0.050
hr / SF4.3750
hr / frame3.1250
hr / panel30
hr / LF1.50
hr / hole0.11.15
hr / each0.04170
hr / each0.04170

Computed over 1,617 observed records across 429 priced estimates across 116 jobs. These are observed rates from real priced estimates — not an industry average and not a benchmark. They are a starting point for your own estimate, never a substitute for one, and they carry no money: labour rates, markup and margin are yours.

Questions

What is an operation allowance?

The labour to perform one unit of a discrete operation: one hole drilled, one stud welded, one bolt installed. Building an estimate from counted operations is far more defensible than a blanket percentage adder.

Why is the drilling p90 so much higher than the median?

Thick material and field conditions. The median of 0.10 hr/hole reflects normal shop drilling; the long tail is heavy plate and awkward access.

How do I count holes?

Off the connection details. Every bolted connection has a hole count per side, and that same count drives the bolt-up hours — so the two should reconcile against each other.